Image of back arrow Back to filtered results

XRN 6155
Update to Meter Removal Process in UKLink

Last Updated
25 Nov 2026
Status
Current
Release Type
Unallocated
Implementation Date
TBC
Proposer CDSP Impacted DSC service area

Customer Change Team Leader uklink@xoserve.com

Summary

When UK-Link processes a Shipper request to remove a device with an effective date earlier than the date of a previously processed meter amendment activity, and no read has been processed within that period, UK Link will process the meter removal, but the meter status will show as LI rather than RE

This means that under this scenario, incorrect detail will flow for that meter status to the applicable IGT / DN customer on their daily delta files.

If we put a process in place whereby the shipper cannot request for the meter to be removed from their responsibility until they have provided the final meter read and any relevant updates, this should prevent the issue from occurring.

Impacted Customer Types

  • Shipper
  • DNO
  • IGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal CP raised 25/11/2026 For approval 09/12/2026
Initial Review Stage not yet reached   N/A
High Level Solution Options Stage not yet reached   N/A
Solution Review Stage not yet reached   N/A
Detailed Design Stage not yet reached   N/A
Evaluation Quotation Reports (EQR) Stage not yet reached   N/A
Business Evaluation Reports (BER) Stage not yet reached   N/A
Change Completion Reports (CCR) Stage not yet reached   N/A

Timeline

Change Proposal raised
25/11/26
Status Awaiting ChMC approval on 09/12/2026
Change development
Solution development
Detailed design
Awaiting delivery
In delivery
Change implemented

Contact the Change Team

Need to get in touch with a member of the Change Team?

You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.