4 February 2026

We’re carrying out our annual disaster recovery test on Saturday 18 and Sunday 19 April 2026

Every year we carry out a disaster recovery test on Gemini

As part of this exercise, we confirm that production Gemini services can be migrated to a secondary data centre location. This ensures that Gemini can continue to operate if we encounter a catastrophic failure with the primary data centre.

This year’s test will take place on Saturday 18 and Sunday 19 April and the activities are scheduled as follows:

Failover from the primary to secondary site

  • Saturday 18 April from 4am – 8am

Failback from the secondary to primary site

  • Sunday 19 April from 4am – 8am

During the above windows Gemini will be unavailable. No contingency processes can be followed, as the system will be completely offline. More information is available below.

Gemini annual DR test information

 

Need support?

If you have any questions about this activity, please raise a support request through our help centre.

Raise a support request 

 

 

 

Raise a support request

Please raise a support request if you have any queries regarding Gemini.

Raise a support request

2026 Gemini disaster recovery test

You can find out more information about the activities involved below.

Find out more

Share this news article