XRN 5602
Releasing of unused capacity under a specific set of circumstances (Modification 0818)
|
Last Updated
|
26 Apr 2023 |
Status
|
Withdrawn
|
|
Release Type
|
Ad-hoc |
Implementation Date
|
TBC
|
| Proposer | Xoserve | Impacted DSC service area |
Service Area 3 (Current Apr 21) Manage updates to customer portfolio |
| Customer Change Team Leader | uklink@xoserve.com |
Summary
Please note that due to a decision by Ofgem to reject Modification 0818 - Releasing of unused capacity under a specific set of circumstances, XRN5602 has been withdrawn.
This change was raised to deliver the requirements set out under UNC Modification 0818 - Releasing of unused capacity under a specific set of circumstances. This Modification has been raised to release unused capacity (only where an SMP meets a specific criteria).
The Change Proposal will implement a process to deliver the Modification 0818 requirements which involves the following:
- A DNO can request that a Shipper reduces a SMPs capacity if the SMP meets a strict criteria and is on an area of the network with restricted capacity available to other Registered Users / end consumers. Please note, the criteria which the SMP would be required to meet is outlined in the Solution section of Modification 0818.
- The relevant Shipper of the SMP will have the opportunity to appeal the reduction in capacity.
- If following the appeal process, a capacity reduction is still required, the Shipper should submit a Supply Point Amendment to reduce the capacity from 01 October in the relevant year.
- If the relevant Shipper does not submit a successful Supply Point Amendment to reduce the capacity to the DNO agreed values by 31 October, the CDSP will reduce the capacity on their behalf.
- MOD 818 is a material change and subject to Ofgem approval.
For further details on the criteria for a site to meet the 0818 process and the appeal process / timelines, please see the Modification which can be found here: https://www.gasgovernance.co.uk/0818
Impacted Customer Types
- Shipper
- DNO
Documents
| Document title | Comment | Last updated | CHMC outcome |
|---|---|---|---|
| Change Proposal | CP raised | 13/01/2023 | Approved at ChMC 11th January 2023 |
| Initial Review | Stage not required | ||
| High Level Solution Options | Stage not required | ||
| Solution Review | Stage not required | ||
| Detailed Design | 3148.2 VO - PO | 19/04/2023 | ChMC approved |
| Evaluation Quotation Reports (EQR) | Stage not yet reached | N/A | |
| Business Evaluation Reports (BER) | Stage not yet reached | N/A | |
| Change Completion Reports (CCR) | Stage not yet reached | N/A |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.