Last Updated
|
29 Mar 2022 |
Status
|
Current
|
Release Type
|
Major |
Implementation Date
|
TBC
|
Proposer | Cadent | Impacted DSC service area |
TBC To be confirmed |
Customer Change Team Leader | uklink@xoserve.com |
Summary
Following Ofgem’s decision to approve UNC Modification 0651‘Changes to Retrospective Data Update Provisions’ a change is needed to progress the delivery of requirements set out in this Modification.
Modification 0651 specifies that the CDSP will facilitate an industry wide Asset Data Cleansing exercise, allowing Shippers an opportunity to correct pre-existing asset data discrepancies by submitting an extract of their respective portfolio to Xoserve. Xoserve will then work collaboratively with Shippers to compare datasets and share outputs before agreeing on the course of action to be taken to apply updates to the Supply Point Register. In addition, 0651 sets out the principles of an enduring Retrospective Update solution which will allow Shippers to correct asset data discrepancies as and when these are identified.
Impacted Customer Types
- IGT
- Shipper
- DNO
Documents
Document title | Comment | Last updated | CHMC outcome |
---|---|---|---|
Change Proposal | Approved | 04//04/2019 | Approved at ChMC 10/04/2019 |
Initial Review | Stage not used | N/A | N/A |
DSG Discussions | N/A | 02/12/2019 | N/A |
High Level Solution Options | Stage not used - Solution Change Pack detailed below | N/A | N/A |
Solution Review | Solution Change Pack Comm Ref: 2844 - RT – PO | 13/10/22 | N/A |
Detailed Design | Stage not yet reached | N/A | N/A |
Evaluation Quotation Reports (EQR) | Stage not yet reached | N/A | N/A |
Business Evaluation Reports (BER) | Stage not yet reached | N/A | N/A |
Change Completion Reports (CCR) (Retro Proof of Concept) | Approved | 13/01/2021 | Retro POC CCR approved |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.