Last Updated
|
13 Sep 2022 |
Status
|
Implemented
|
Release Type
|
Ad-hoc |
Implementation Date
|
18
Jul
2022
|
Proposer | Northern Gas | Impacted DSC service area |
TBC To be confirmed |
Customer Change Team Leader | uklink@xoserve.com |
Summary
As part of XRN5014, the effected Supply Meter Points within the HyDeploy2 Live Pilot had an “AQ Backstop” set to retain the integrity of the AQ while the supply meter point was consuming 20% Hydrogen Blend.
HyDeploy2 Live Pilot has now finished, so there is a need for the ‘AQ Backstop’ to be removed, ensured that there has been no detrimental impact on the SMP AQs values, and the balancing/settlement process has been unaffected, as per original project plan.
Discussion are ongoing and confirmation from NGN when the invoicing payments will stop will dictate the delivery date for this change as both would need to be in alignment.
Confirm that no backend processes are still utilising the HyDeploy2 flag (as flag needs to remain) to treat these MPRN’s differently to a standard MPRN.
This Change is part of XRN 5014 - Facilitating HyDeploy2 Live Pilot
Impacted Customer Types
- Shipper
- DNO
Documents
Document title | Comment | Last updated | CHMC outcome |
---|---|---|---|
Change Proposal | Approved | 13/06/2022 | CP approved at ChMC on 08/06/2022 |
Initial Review | Stage not required | N/A | N/A |
DSG Discussion | N/A | 27/06/2022 | N/A |
High Level Solution Options | Stage not required | N/A | N/A |
Solution Review | Stage not required | N/A | N/A |
Detailed Design | Approved | 19/07/2022 | Approved at July 2022 ChMC |
Evaluation Quotation Reports (EQR) | Stage not required | N/A | N/A |
Business Evaluation Reports (BER) | Stage not required | N/A | N/A |
Change Completion Report (CCR) | Approved | 12/09/2022 | CCR approved at ChMC 07/09/2022 |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.