XRN 5682
February 24 Major Release

Last Updated
14 May 2024
Status
Implemented
Release Type
Major
Implementation Date
24 Feb 2024
Proposer Xoserve Impacted DSC service area

N/A

Not applicable

Customer Change Team Leader uklink@xoserve.com

Summary

This change proposal has been raised to create a parent XRN for the February 24 Major Release.  There are 3 changes within this release:

  • XRN5604 UNC Modification 0811S Shipper Agreed Read (SAR)
    Exceptions Process
  • XRN5605 IGT Modification 159 – Amendments to the must read
    process
  • XRN5607 Update to AQ Correction Processes (Modification
    0816S)
XRN 5604
Shipper Agreed Read (SAR) exceptions process (Modification 0811S)

Implemented

View Change Proposal
This change has been raised in to deliver the requirements set out under UNC Modification 0811S, in order to provide a remedy for SARs that have failed to be progressed (exceptions) within a reasonable period, to be proactively managed by the Central...
XRN 5605
Amendments to the must read process (IGT159V)

Implemented

View Change Proposal
This Change Proposal has been raised to deliver the requirements set out under IGT UNC Modification 159V – Amendments to the must read process. This Modification was raised to update the IGT must read process to include timescales for a site to enter...
XRN 5607
Update to the AQ correction processes (Modification 0816S)

Implemented

View Change Proposal
This Change Proposal has been raised to deliver the requirements set out under UNC Modification 0816 - Update to AQ correction processes. This Modification proposes to add two further ‘eligible causes’ to the Annual Quantity (AQ) amendment process wi...

Impacted Customer Types

  • Shipper
  • DNO

Documents

Document title Comment Last updated CHMC outcome
Change Proposal CP Raised 13/10/2023 Presented for information at ChMC 11/10/23
DSG Discussion

Meeting - 20/11/23

Meeting - 18/12/23

Meeting - 22/01/24

Meeting - 25/03/24

Meeting - 22/04/24

29/04/24

N/A
Project Update N/A 14/05/2024  
Evaluation Quotation Reports (EQR) Stage not required N/A N/A
Business Evaluation Reports (BER) For approval 16/10/2023 Approved at ChMC 11/10/23
Implementation Approach N/A 13/12/2023 Presented for information at ChMC 13/12/23
February 24 Release e-learning Online e-learning course 12/02/2024 N/A
Change Completion Reports (CCR) For Approval 14/05/24 Approved at ChMC 08/05/23

Timeline

Change Proposal raised
29/09/23
Status CP to go to ChMC for information on 11/10/23
Change development
29/09/23
Status Stage not required
Solution development
29/09/23
Status Stage not required, see individual changes
Detailed design
29/09/23
Status Stage not required, see individual changes
Awaiting delivery
29/09/23
Status BER approved at ChMC on 11/10/23
In delivery
11/10/23
Status Implementation date set 24/02/24
Change implemented
24/02/24

Contact the Change Team