Summary

As part of MHHS the programme is coordinating a series of production data backups on the 19th August. Although the MHHS programme is limited to Electricity at the moment it has been suggested that we as the GRDA take a copy of our portfolio on this day also.

 

Xoserve will be required to take and store a snapshot of production data on the 19thAugust 2023.  This is similar to snapshots taken in January and November 2020.

 

This will be used for future coordinated testing purposes and will be the new industry baseline.

Impacted Customer Types

  • Shipper
  • DNO
  • IGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal CP Raised 10/08/23 Approved at ChMC 09/08/23
DSG Discussion N/A 31/08/23 N/A
Evaluation Quotation Reports (EQR) Stage not required   N/A
Business Evaluation Reports (BER) N/A 15/09/2023 Approved at ChMC 13/09/23
Change Completion Reports (CCR) N/A 16/10/2023 Approved at ChMC 11/10/23

Timeline

Change Proposal raised
02/08/23
Change development
Approved into development 09/08/23
Solution development
01/01/01
Status Stage not required
Detailed design
01/01/01
Status Stage not required
Awaiting delivery
01/01/01
Status Stage not required
In delivery
Due for implementation on 19th August 09/08/23
Status Awaiting implementation
Change implemented
Implementation successful 19/08/23